Galileo Mission: ASP Equipment GmbH demonstrates expertise in the development of Power Supply Systems for Space Applications

With the delivery of the Proto-Flight Model of the Centralized Power Supply Unit (CPSU) for the 2nd Generation of the Galileo Mission (European satellite navigation) of the European Space Agency (ESA), ASP has once again demonstrated its expertise in the development and manufacturing of Power Supply Systems for space applications.

Major milestones were achieved throughout this development:
• September 2021: Requirements Review
• July 2022: Preliminary Design Review
• December 2022: Delivery of the Elegant Breadboard
• November 2023: Critical Design Review
• August 2024: Delivery of the Engineering Qualification Model
• February 2025: Delivery of the Proto-Flight Model

Now that the CPSU has been successfully qualified, the production phase for 5 Flight Models has already begun. We are excited to continue supporting the Galileo Mission with additional CPSU Flight Models.

Galileo Mission: ASP demonstrates expertise

Successful Space Industry Day 🚀at ASP Enthralls Visitors

ASP Equipment wins the ESA Supplier Award

Visit by State Secretary Dr. Patrick Rapp and Member of Parliament Klaus Hoher at ASP

PLATO: ESA Supplier Evaluation Report

Ariane 6: Successful Launch

Looking Back: Summer Party

8. ZF Company Run

500th High-Performance Amplifier (HPA) delivered

PLATO Project: Another Successful Milestone

Mass Change Project: Next Milestone successfully achieved

ASP signs Mass Change contract